Release Notes V-Cube & V-Cube+ 6.0.2

Collax V-Cube / Collax V-Cube+
28.07.2010

Installation Notes

Install Update within Cluster

Please read the following release notes carefully, before continuing. When installing this update on a Collax V-Cube+ cluster the following steps have to be performed:

Note: If starting the update from 6.1.8 to 6.1.10 no down time of the running virtual machines or applications is required.

Procedure

  1. If the nodes have the version 6.1.8 or prior: Please read the appropriate notes for that release including the documented procedure first.
  2. The software packages can be downloaded whithin a running Cluster to prepare the update and minimize the planned downtime. Go to the local administration of each node and access the form System Operation → Software → Systemupdate. Then click Get Package List. This will download the list of available update packages. The successful update of the package list is indicated by the message Done!. Click Get Packages. If the packages are downloaded successfully then the message Done! will be displayed.
  3. Put one node into standby mode. Go to Status/Maintenance → Cluster Nodes and execute the action Standby. Please wait until the cluster resources are stopped or the VMs are migrated.
  4. Now, put this node into maintenance mode. Go to the dialog Status/Maintenance → Cluster Services and stop the service HA Cluster for this node.
  5. Click Install within the dialog Systembetrieb → Software → Systemupdate to install all update packages. The end of this process is indicated by the message Done!.
  6. If a new kernel is going to be installed the system will be rebooted automatically after installing the update. An appropriate note will be shown. Please wait for the reboot in that case.
  7. Start the service HA Cluster on the node that has been updated. Please wait until the service ist started and information about Cluster Resources are available before you proceed with the next step.
  8. Once the service HA Cluster has been started resume the node by using the action Set active within the dialog Status/maintenance → Cluster Nodes .
  9. Afterwards check the status of the eSAN-disk synchronization in the form Cluster Administration → Virtual Hard Disks. Do not continue with the next step until the column Status shows 100% or OK for all eSAN disks.
  10. Please repeat this procedure from step 2 on the next node that needs to be updated.

Install Update from Version 6.0.10 within Cluster

Please read the following release notes carefully, before continuing. Note that when installing this update on a Collax Inter-V cluster the following steps have to be performed:

Procedure

  1. This version is deprecated and does not receive further support.
  2. Please shut down all virtual machines within the cluster management gui before continuing with the following steps. Please consider to disable the shutdown event tracker for Windows operating systems before shutting down the virtual machine.
  3. Put all nodes into standby mode. Go to Status/Maintenance → Cluster Nodes and execute the action Standby. Please wait until the cluster resources are stopped.
  4. Put one node into maintenance mode. Go to the dialog Status/Maintenance → Cluster Services and stop the service HA Cluster for this node.
  5. Go to the local administration of this node and access the form System Operation → Software → Systemupdate. Then click Get Package List. This will download the list of available update packages. The successful update of the package list is indicated by the message Done!.
  6. Click Get Packages. If the packages are downloaded successfully then the message Done! will be displayed.
  7. Click Install. This action installs all update packages. The end of this process is indicated by the message Done!.
  8. A new kernel is going to be installed. The system will be rebooted automatically after installing the update. An appropriate note will be shown if the update process is completed.
  9. After the reboot start the service HA Cluster of the node again: Go to the cluster administration form Status/Maintenance → Cluster services. Please wait until information about Cluster Resources are available.
  10. Repeat the steps 3 to 8 for the next cluster node.
  11. Once all cluster nodes are updated resume them one by one by using the action Set active within the dialog Status/maintenance → Cluster Nodes .
  12. Next check the status of the eSAN disk synchronization in the form Cluster Administration → Virtual Hard Disks. Do not continue with the next step until the column Status shows 100% or OK for all eSAN disks.
  13. If all nodes within the cluster are updated and active the virtual machines can be started again.

Install Update on a Collax V-Cube

To install this update on a Collax V-Cube without a Cluster interconnection please follow these steps:

Procedure

  1. Please read this document before proceeding to the next step.
  2. In the administration interface go to System → System Operation → Software → System Update and then click Get Package List. This will then download the listed update packages. The successful update of the package list is indicated by the message “Done!”.
  3. Click Get Packages to download the software packages.
  4. Click Install. This action installs the update. The end of this process is indicated by the message Done!.
  5. A new kernel is going to be installed. The system will be rebooted automatically after installing the update. An appropriate note will be shown once the update process is completed.
  6. If the server is updated and booted the virtual machines can be started again.

New in this Version

Virtualization: New Version of Kernel-based Virtual Maschine (KVM)

With this update of Collax V-Cube the version 0.12.4 of the Kernel-based Virtual machine (KVM) is going to be installed. Amongst others this version improves memory processing of virtual machines. Up to now the memory consumption of a VM could exceed the amount assigned by the Collax V-Cube. This behaviour is going to be prevented with this update of KVM.

Note: During the update of Collax V-Cube virtual machines will NOT be restarted. To make the new version 0.12.4 usable, running virtual maschines shall be shut down and started. The reboot of a virtual maschine does not deploy the new version of KVM.

Virtualization: New version Collax Migration Tool 1.7

To virtualize many server on one physical machine has a lot advantages. With the Collax Migration Tool server disks can easily be migrated into the Collax Virtualization. Now the version 1.7 of the tool brings improvements for the migration via network. It accelerates the transfer rate within gigabit networks upto 50 MBit/s.

Misc: Enhancement of Administration Tool setip for console

The tool “setip” provides settings for the network and for important services via console within an easy to use menu. With this update the tool offers network settings for bridge devices wich is helpful when setting up Collax V-Cube.

Issues Fixed in this Version

Security: GNU data type library glib2

In the source code of glib2 security holes have been discovered. These holes will be closed within this Collax software update.

A patch for glib2 2.18.2 is going to be installed and fixes the assigned Common Vulnerabilities and Exposures (CVE) numbers:

CVE-2009-3289

Security: Python Language Interpreter and Runtime

In the source code of the Python language interpreter and runtime security holes have been discovered. These holes will be closed within this Collax software update to version 2.6.5.

Assigned Common Vulnerabilities and Exposures (CVE) numbers:

CVE-2010-1449 CVE-2010-1450 CVE-2010-1634